1 Common Service Tunnel Phase 3B at Downtown Marina Bay ( CE & SB2) Structural Works S$ 4.8 million July 2011 ~ Dec 2013 Civil Tech Pte Ltd
2 C926-Prison & Stadium Shaft (KT12/S0001) Reinforced Concrete Works S$ 800K Mar 2012 ~ Jan 2013 Kok Tong Construction Pte Ltd
3 C927-Bedok Reservoir MRT Station & Tunnels for Downtown Line Stage 3. Supply Labour & Mat’L for Construction of TBM Eyes & Temporary Canal and Capping Beam. S$ 1.8 million May 2012 ~ Sep 2013 Cooperative Muratorie Cementishi Ravenna
4 HDB PWS (KTC13/M0002)-PUB Earthworks and Outletdrain No.04 at Punggol West. ( Phase 1 ) Supply Skilled Labour and Mat’L for RC Works & some V.O Works. S$ 2.1 million Nov 2012 ~ Sep 2013 KTC Civil Engineering & Construction Pte Ltd
5 Toh Guan Road East 5A Warehouse Structural Works & Labour only for RC Work S$ 1.2 million June 2013 ~ Dec 2013 E C Builders Pte Ltd
6 4 Pandan Ave – 5 Storey Warehouse Structural Works & Labour only for RC Work S$ 2.4 million Nov 2013 ~ Oct 2014 E C Builders Pte Ltd
7 Contract LTAW258 (KTC13/M0003) Wenya Bus Depot Supply Skilled Worker and Formwork Mat’L for RC Works. S$ 3.5 million Dec 2013 ~ June 2015 KTC Civil Engineering & Construction Pte Ltd
8 Lots 00789X PT, 00794C, 00795M, 00805M,00796W & 00800K PT, MK30 at Greenwich Drive (Paya Lebar Planning Area) Structural Works & Labour only for RC Work S$ 2.2 million June 2014 ~ Dec 2014 E C Builders Pte Ltd
9 Proposed Design And Build For A 6-Storey Single User Industrial Development With Open Carparks At No.15 Bukit Batok St 22 Structural Works & Labour only for RC Work S$ 400K June 2014 ~ Present Sanwah Construction Pte Ltd
10 Construction of Container Berths P36-P41 and Stacking Yard at Pasir Pajang Terminal, Phase iii (Wharf Drainage). Supply Skilled Labour And Equipment For Civil Works And Decking Works S$ 950k Feb 2015 ~ Preent Poh Keong Construction Pte Ltd
11 Rh Hdb Changi Staging Yard, Located At Changi Aviation Park Road Supply Skilled Worker and Formwork Mat’L for RC Works. S$ 2 million Feb 2015 ~ Present Kok Tong Construction Pte Ltd
12 Loyang Drive Lamp Post 5 / Loyang Drive Road Drainage Works S$ 650K June 2015 ~ Present KTC Civil Engineering & Construction Pte Ltd
13 Tampines AVE 9 Drainage Works S$ 1.4 million Aug 2015 ~ on going KTC Civil Engineering & Construction Pte Ltd

 

17th March 2015

 

S/N Name of Projects Type of Work Value of Work Contract Period Client
1 Common Service Tunnel Phase 3B at Downtown Marina Bay Structural Works S$ 3.2 million July 2011 ~ Dec 2012 Civil Tech Pte Ltd
2 Common Service Tunnel Phase 3B at Downtown Marina Bay ( SB2) Form Work & Concrete R C Work S$ 1.5 million Dec 2012 ~ Dec 2013 Civil Tech Pte Ltd
3 C926-Prison & Stadium Shaft (KT12/S0001) Reinforced Concrete Works S$ 800K Mar 2012 ~ Jan 2013 Kok Tong Construction Pte Ltd
4 C927-Bedok Reservoir MRT Station & Tunnels for Downtown Line Stage 3. Supply Labour & Mat’L for Construction of TBM Eyes & Temporary Canal and Capping Beam. S$ 1.8 million May 2012 ~ Sep 2013 Cooperative Muratorie Cementishi Ravenna
5 RD249 ( KTC12/M0001) Temporary Bus Park at Upper Changi Road Est. Noise Barrier Footing ( Supply Skills Labour & Formwork Mat’L for RC Work) S$ 500k Nov 2012 ~ Apr 2013 KTC Civil Engineering & Construction Pte Ltd
6 HDB PWS (KTC13/M0002)-PUB Earthworks and Outletdrain No.04 at Punggol West. ( Phase 1 ) Supply Skilled Labour and Mat’L for RC Works & some V.O Works. S$ 2.1 million Nov 2012 ~ Sep 2013 KTC Civil Engineering & Construction Pte Ltd
7 Toh Guan Road East 5A Warehouse Structural Works & Labour only for RC Work S$ 1.2 million June 2013 ~ Dec 2013 E C Builders Pte Ltd
8 4 Pandan Ave – 5 Storey Warehouse Structural Works & Labour only for RC Work S$ 2.4 million Nov 2013 ~ Oct 2014 E C Builders Pte Ltd
9 Proposed Overall Drainage Catchment And Platform Level For Yishun N4. Supply Skilled Worker and Formwork Mat’L for RC Works. S$ 0.4 million Mar 2014 ~ Nov 2014 KTC Civil Engineering & Construction Pte Ltd
10 Contract LTAW258 (KTC13/M0003) Wenya Bus Depot Supply Skilled Worker and Formwork Mat’L for RC Works. S$ 3.5 million Dec 2013 ~ June 2015 KTC Civil Engineering & Construction Pte Ltd
11 Lots 00789X PT, 00794C, 00795M, 00805M,00796W & 00800K PT, MK30 at Greenwich Drive (Paya Lebar Planning Area) Structural Works & Labour only for RC Work S$ 2.2 million June 2014 ~ Dec 2014 E C Builders Pte Ltd
12 Proposed Design And Build For A 6-Storey Single User Industrial Development With Open Carparks At No.15 Bukit Batok St 22 Structural Works & Labour only for RC Work S$ 400K June 2014 ~ Present SANWAH CONSTRUCTION PTE LTD
13 Contact Ew-2-Design, Construction And Completion Of Esat-West Transmission Cable Tunnel Supply Skilled Worker and Formwork Mat’L for RC Works. S$ 300K Mar 2014 ~May 2014 & DEC 2014 ~ Present SK E & C (Singapore Branch)
14 Construction Of Container Berths P36-P41 And Stacking Yard At Pasir Pajang Terminal, Phase iii (Wharf Drainage). Supply Skilled Labour And Equipment For Civil Works And Decking Works S$ 950k Feb 2015 ~ Present Poh Keong Construction Pte Ltd
15 Rh Hdb Changi Staging Yard, Located At Changi Aviation Park Road Supply Skilled Worker and Formwork Mat’L for RC Works. S$ 500k Feb 2015 ~ Present KTC Civil Engineering & Construction Pte Ltd